Phase 4 UAT to Go Live Workflow

Workflow Verified Tue Apr 28 2026 00:00:00 GMT+0000 (Coordinated Universal Time) For: AdminSystemITSupportFinanceAccountingTelemedicineAdmin Source: phase-4-uat-documents/หนังสือส่งมอบงานงวดที่ 4 - TICC - 03042569.pdf, phase-4-uat-documents/3. Telemed/5. Telemed - เอกสารข้อตกลงร่วมการใช้ระบบสารสนเทศจริง.pdf Updated Tue Apr 28 2026 00:00:00 GMT+0000 (Coordinated Universal Time)

Phase 4 UAT to Go Live Workflow

Overview

Generic evidence workflow used by Phase 4 delivery documents to move a system from testing and training into go-live readiness.

Steps

  1. Define delivery scope by system: MEDHIS, Odoo ERP, or Telemedicine.
  2. Install or prepare target environment such as Staging/UAT or Production.
  3. Perform internal smoke/pre-UAT tests.
  4. Train user groups and administrators.
  5. Conduct UAT with real users or key users.
  6. Record UAT result as ผ่าน / สำเร็จ or capture issue.
  7. Run simulation if required, such as Queue floor simulation or Telemedicine room simulation.
  8. Verify data migration or sync readiness.
  9. Verify infrastructure, network, server, device, and support-channel readiness.
  10. Verify security, user rights, backup, and recovery plan.
  11. Hold go-live readiness meeting with responsible parties.
  12. Confirm go-live date/time.
  13. Execute go-live.
  14. Provide post-go-live support and issue tracking.
  15. Include signed annexes or delivery confirmations in package.

Readiness Checklist

ItemRequired Evidence
UATTest result with user/key-user confirmation
TrainingTraining schedule and attendance evidence
InfrastructureServer/network/device readiness
DataMigration or sync verification
ManualUser/admin/IT manuals delivered
SupportHelpdesk or support channel prepared
SecurityUser rights and access control reviewed
BackupBackup and recovery plan checked